Fit-out of Igralife recreation centre

Int-Ext Company has completed the fit-out of Igralife recreation centre occupying 1348m2 at Pravoberezhnaya str., 1b (Kapitoly Trade Centre).

Besides design works, we have conducted the following construction works:

Arrangement of bowling area
  • wall and floor sound insulation
  • installation of reinforced concrete base for the bowling area
  • installation of electric power supply system including a UPS and a surge protector
  • installation of HVAC system
  • installing wave-shaped suspended ceilings
  • plastering and painting works
  • installation of bowling area's glass partition

 

Kitchen arrangement, fit-out of bar and restaurant areas
  • waterproofing works
  • plumbing, installing a grease trap
  • installation of electric power supply system and structured cabling system
  • installation of ventilation system
  • raised floor installation
  • floor covering works
  • spackling and painting works
  • installation of glass partitions in the cafe area
  • installing suspended ceilings

 

Child maze and arcade machines areas
  • floor screeding works
  • cladding of ceramic granite tiles
  • installing electric power supply system and structured cabling system
  • installation of ventilation system
  • plastering and painting works

 

Motodrome area interior fit-out
  • floor screed installing and polishing
  • installation of electric power supply system and structured cabling system
  • ventilation system installation
  • installation of round-shaped multi-level plasterboard ceiling
  • spackling and painting of walls and the ceiling

 

Entrance area fit-out
  • floor sand-cement screeding
  • installation of ceramic granite tiles
  • installation of engineering systems
  • building plasterboard partitions
  • installing the plasterboard suspended ceiling
  • plastering and painting works
  • fit-out of the entrance door frame

 

Office premises, engineering and utility rooms, sanitary facilities
  • fit-out of the administration offices
  • building the utility and technical rooms
  • construction of WCs including all related works